Grand Prairie, Texas map
A restaurant tenant buildout inside a new shell, not shell construction, at one facility; 4,800 sq. ft.; stated value $600,000. Project contacts were listed, but the tenant-buildout general contractor was not publicly identified. No specific qualifications were stated. A project filing is dated April 17, 2026, and filed construction completion is December 15, 2026. A May 15 announcement targeted a mid-December opening, while a live location page still said “coming soon” and offered pre-opening event registration when checked October 19; opening and construction completion are separate milestones. The available project status does not establish physical progress. Completion confidence is medium-low because the filed schedule and opening announcement align, but no recent interior-finishing or inspection evidence was found. Call now to clarify buildout responsibility and whether the December schedule remains realistic.